The project consisted of the construction of three reservoirs and approximately 40 miles of various size pipeline for nine villages in the Belize River Valley.

Roughton was appointed to carry out the following:

  • Detailed engineering survey of the layout of the route, for installing the distribution network and mains, interconnective the nine villages
  • Review two existing tank designs - 2 x 20,999 gallons, ground and elevated
  • Prepare one new tank design - 50,000 gallons, ground
  • Provide construction supervision services for erecting three tanks together with the installation of approximately forty miles of PVC main, within and between the villages