Project

email us: info@roughton.com

Cross River State RAMP 2, Nigeria

Client: Cross River State Ministry of Works

The overall objective of the project was the upgrading of gravel feeder roads to all weather access road standard with two-lane 6.0m wide carriageway and 1.0m wide shoulders with double surface dressed bituminous pavement.

The work was split into three seperate contracts:

  • Conceptual design studies and supervision of works
  • Institutional strengthening and baseline studies
  • Project Audit

Roughton was appointed to undertake the second contract - Institutional strengthening and baseline studies, which included the following services:

  • Technical assistance
  • Training
  • Studies - road reclassification, bridge inventory, baseline for project monitoring indicators

In addition to:

  • Construction supervision of upgrading works of the roads

 

Footer