email us: info@roughton.com
Client: ALANet Global
The Masiaka - Bo Road is a 160km paved road with two lanes in each direction and ten bridges along the route. It was completed in 2010 and the Client required an audit to be carried out to determine that the final acceptance certificate payment should be made.
The audit investigated whether the construction met the technical specifications. Various site tests were carried out and the results analysed and presented to the Funder for consideration.
Roughton undertook the following: